Estimating the quantity of bricks is necessary for the rate analysis.
Quantity Estimation for Brick Masonry - To analyze the rate of brick masonry, 1m3 of brick masonry is taken:
1. Number of bricks for 1 cubic meter of brick masonry:
For 1m3 of brick masonry, the number of typical size of bricks must be 494.
2. Quantity of mortar for 1m3 of brick masonry:
For 1m3 of brickwork, the quantity of the mortar should be 25 – 30%, i.e. 0.25m3 – 0.3m3 of cement masonry. For this purpose, cement mortar is selected as 0.3m3 .
Labor Estimation for Brick Masonry:
Labors which are essential for brick masonry belong to mason for brick work, labours for transmitting materials (sand, cement, bricks, and water), mixing and transporting mortar.
The quantity of labor is provided as requirement of labour in longer period for 1m3 of brick masonry.